All 224 white sandblasted architectural precast concrete sandwich panels for this phase of the project were quickly erected in only 18 working days.

Panels were insulated using 2 inches of rigid polystyrene insulated between the inner and outer wythes of precast concrete.

Horizontal rustication (false) joints, vertical mullion panels and set back dark coloured windows created a highly distinctive exterior for the owner’s building.

Credits:
Owner: Les Placements Compotoro
Architect: Saroli Palumbo
Engineer: Structure Acier Cartier (Ing.)
Contractor: Les Excavations DP Ltée
Precaster: SARAMAC

 