Nox-Crete GCP Applied Technologies ACT JVI, Inc. Cresset Chemical UltraSpan CME Max USA Corp Euclid Splice Sleeve
Oakville GO Station Parking Structure
Oakville, Ontario

Situated in the Town of Oakville, the Oakville GO Station Parking Structure is located at the south side of the existing Lakeshore West Commuter rail corridor, providing parking capacity to approximately 1,400 vehicles.

The precast concrete structural system was selected as the original design-build concept to reduce the construction schedule, minimize interruptions to the station, and provide an appropriate level of passive security.

Approximately 8,350 m3 of precast concrete was used on this project, totalling 22,000 tons. The six-level precast structure is 133 m (long) x 55 m (wide) x 21.9 m (high). Modular configuration of precast allows for rapid construction. The total construction time of this project was approximately 20 months, allowing Metrolinx/GO Transit to accommodate more parking customers sooner. Construction began in January 2011 and the project was substantially completed in September 2012.

With a wide selection of custom profiles, colours, textures, and patterns, the building was able to achieve interesting facades, which would be difficult to accomplish in a cast-in-place concrete design.

The long span structural members allowed for a reduced number of columns, as well as increased openness and visual sightlines and security. Additionally, the precast system reduced long-term life cycle costs by improving the durability of the structure, which was increased by a low permeability concrete topping with corrosion inhibitors.

Precast concrete resulted in less impact on the area surrounding the site (reduced truck movements, less dust, less construction equipment required on site, and less noise). The construction site is located next to a train station that services 13,000 passengers per day, which remained operational during construction with no interruptions.

Precast was formed using unique architectural forms, textures, and colours. To minimize the scale of the structure and to compliment the town’s surroundings, the facades of the parking structure features strong, multi-level columns, arches, stainless steel guard rails, and metal framed window grilles.

The parking structure also features a variety of pigments and textures, including sandblasted, exposed aggregate, and form-finish. These options are more economical when compared to using cast-in-place concrete.

The project included the following unique features:

  • The building was designed to a LEED Silver standard and includes green design components such as a white reflective roof, rooftop photovoltaic system, bicycle storage, car battery charging, and a car counting system.
  • The structure is connected to the existing train platforms and station building by a pedestrian underpass walkway leading from the underground elevator lobby. In addition, four electric elevators are provided for barrier-free access to the platforms and station buildings.
  • Oil-grit separators to remove contaminants from collected stormwater.
  • Landscaped parkette with engineered bioswale on the south end to provides some pre-treatment for surface run-off.
  • 250 kW photovoltaic arrays to provide power for the provincial feed-in tariff (FIT) program.
  • White thermoplastic polyolefin (TPO) membrane to reduce heat island effect.
  • LED interior and exterior lighting for lower energy consumption.
Owner:
Architect:
Precast Supplier:
General Contractor:
Structural Engineer:
© CPCI 2012. All rights reserved.
Ottawa East Hockey CampGoalie Training Ottawa